Stage 4
2025-08-26
Wedge Rd. Skye construction continues to progress and we are pleased to announce construction commencement of Stage 4 at Wedge Rd.
Stage 4 Titles are forecast for Q1 2026.
If you have any queries regarding your block at Wedge Rd, we recommend speaking with your conveyancer in the first instance. If you would like to reach out to us, please contact us on 0473 630 484 or email us at hello@wedgerd.attractor.solutions
November 2025:
- Concrete works continuing
- Power and NBN installation underway
October 2025:
- Kerb works are completed.
- Concrete works are underway.
- asphalt to be laid down shortly.
- Electrical reticulation to commence shortly.
September 2025:
- Road crossings complete.
- Road stabilisation and adding the next layer of road (class 3) is underway.
August 2025:
- Drainage works due to complete shortly and service trenching to commence.
July 2025:
- Melbourne Water drainage works underway.
June 2025:
- Road stabilisation works underway.
- Drainage works to commence shortly.
May 2025:
- Sewer works have completed.
- Drainage works to commence shortly.
April 2025:
- Bulk earthworks have completed.
- Sewer works have commenced and are ongoing. Drainage works to commence shortly.
March 2025:
- Construction has commenced and bulk earthworks are underway.
- Sewer works to commence in the coming weeks.